Setting up a Basic Microsoft Project Plan |
First published Dec 05 |
Neville Turbit - Project Perfect |
Rating |
|
![]()
Many people will argue that this is not the most correct way to produce a project plan. I agree. Producing a complex project plan is a complex process. This is a simple process and as such, makes simplifications. Once people know the basic rules, they can understand when to break them. The intention is to teach people to drive before you put them on a race track.
![]()
This is fundamental to understanding how to set up a project plan.
In Microsoft Project a milestone is a task with zero duration.
![]()
The following are examples of tasks:
![]()
![]()
The WBS is produced by breaking down the work into logical chunks. Typically this means major chunks of work. Ask yourself if you can put a one or two word label on a piece of work? Is it fairly self contained? Building on the example above, it may be:
One of the main reasons for producing a WBS is to focus your thinking. Take a top down view and document the major work areas. You can then subdivide even further is the major work areas are too big.
Another way to approach the WBS is to break it down into phases. For example, Phase 1 may be both feasibility and requirements. Whilst it is a valid approach, I would make Phase 1 a top level, and Feasibility and Requirements second levels.
The next step is for the project team to define all the deliverables. This includes internal and external deliverables.
External deliverables include amongst other things, implemented software, products for sale and project reviews. Internal deliverables include things like weekly reports, specifications, presentations and test plans. You can develop a checklist over time to use with teams.
![]()
Now you have the list of deliverables, how are you going to guarantee quality? For each deliverable determine what quality process will apply. It can be testing, peer review, senior management approval or whatever.
![]()
All the deliverables go into a project plan as milestones. A second set of milestones are the deliverables ready for QA. For example “Report ready for peer review”. These occur close to the final deliverable but allow time for rework.
Add all the tasks or actions required to produce the deliverables. Estimate the time for each task. Don’t fall into the trap of thinking “if all goes well it will take …”. When did every task in a project “go well”? Be realistic. Some tasks will go to plan and some will take longer. Some may even take less time but these rarely cancel out the overruns.
The other timing aspect is to understand you can almost never predict all the work required. There will be tasks that become evident only after the project is well underway. If the future is misty, make allowance in the plan for unspecified tasks.
Also look for any milestones along the way. For example if a requirements document is to be produced by holding workshops, a milestone may be “Workshops complete”. Add these to the plan.
![]()
Now you can start to add dependencies. Look for what needs to be done before each step can be undertaken. Create your dependencies. This may lead to changing the order in your Gantt chare to make it more logical. You might even want to create another level in your WBS to clearly identify a group of activities.
For example, you may have a WBS heading called “Feasibility”. When you add your tasks and milestones, you realize that there are two major chunks of work.
It may be worth creating two levels called “Workshops” and “Report”
![]()
You can now work out who is going to do all this work. Add resources to the tasks. When it gets to milestones, only put one name, and make sure it is the person responsible for delivery. Resource leveling and allocation is another topic and will not be covered in this basic white paper.
![]()
When you have reached this point, you can check the plan to make sure it is well structured. Here ten checks to carry out:
![]()
ConclusionIf you can get a plan in place that follows the steps above, you are well on the way to having a solid plan to work to. Many organisations struggle to get this far. Once you have completed one or two plans you can start to get more sophisticated in your planning. There are books and information available that will take you to the next level but first you have to get the basics right.
![]()