Neville Turbit - Project Perfect
|
 |
|
|
|
Scope
v
Time
&
Cost
When people talk about scope, they immediately think time and
cost. Time and cost are outputs of scope. Determining scope is a different
exercise. In the context of this white paper, when we talk about defining
the scope, we are talking about developing a common understanding as to what
is included in, or excluded from, a project. We are not talking about deciding
how long it will take, or how much it will cost. That comes after the scope
is defined.
|
If we were looking for a car, we would first define the
scope. For example we want a 4-cylinder front wheel drive with seating
for 2 adults and 2 children, and less than 2 years old. Maybe you also
want it to be a red convertible.
Having defined the scope, you can calculate cost and time.
How much you will have to spend and how long you will take to buy it.
If you get the scope wrong, the time and cost will be wrong.
|

|

Why
is
Scope
important?
Anyone who has ever done a project will have tales of how scope
changes caused grief. Scope is bound to change, and this is to be expected.
As the detail becomes clearer, more complications creep in. These are not
foreseeable at the start and hopefully we build in a contingency for what
we cannot see.
The scope changes that usually cause problems are those where
the perception of what was in and out of scope was different between various
parties. The Project Manager assumed there would only be four or five reports,
and the business assumed ten to twenty. Nobody felt it was worth talking about
because they assumed the other person thought the same way they did.

How
Scope
is
usually
defined
Scope definitions often account for a paragraph or two in a
Business Case or Project Charter. Often, they are qualitative and/or focus
on general statements.
"We will improve service by providing an information system to respond
to customer inquiries." Is it a real time system? Is it all screen-based?
What reports can be produced? Where does the information
come from? What manipulation is required for the data? Is all
the data compatible? Do you want to generate standard letters?
How many letters? How customisable are the letters? Do you want
to store the questions? Do you want to store the answers? Etc.
etc. etc.

Define
the
Outcome
We will cover several different ways to successfully define
scope. All should start with an agreement on the outcome. The outcome is the
change that will occur when the project is complete. Examples are:
- We will be able to answer customer queries regarding statements over
the phone.
- All licensing details will be accessible on-line and we will be able
to identify when they are due.
Assumptions
In order to define the scope, there will be assumptions that
need to be made. There is no point in waiting until everything is clear to
define scope. By that time, the project will probably be finished. Each of
these assumptions should be documented and followed up at a later date to
validate the scope. If the assumption is false, it may have an impact on the
scope.

Which
way
to
define
Scope?
There are numerous ways to define. Ideally several ways should
be used. Each looks at the situation from a different perspective and will
elicit different information. We look at three main ways in this paper. They
are:
- Define Deliverables
- Define Functionality and Data
- Define Technical Structure

Define
Deliverables
One method to focus people on the scope, is to define the internal
and external deliverables.
- External deliverables are things the project delivers to the users e.g.
screens and reports. Users typically think of a system in these terms. It
also includes any hardware or software required by the users or the project
team.
- Internal deliverables are things the project generates internally e.g.
Project Charter, Business Requirement Specification etc.
It is likely that the users will not be absolutely clear on
all the deliverables. In this situation you can make generic assumptions.
For example, you might not know exactly what reports are required but you
allow for 12 unspecified reports.
Once the external deliverables are defined, the Project Manager
can define the internal deliverables.

Example
External
Deliverables:
| Name |
Description |
| License Detail Screen. |
Screen to enter and view license details |
| Company Summary Screen |
Screen to view all licenses issued by a particular company. Facility
to drill down to License Detail Screen. |
| License Due Report |
Report listing all licenses due in the next period. Facility to select
a period e.g. 1 week, 4 weeks, quarter |
| 5 Reports |
Allow for 5 unspecified reports |
| Server |
Server to run the application |
| Etc. |
|
Example
Internal
Deliverables
| Name |
Description |
| Project Charter |
Document identifying how the project will be managed |
| Business Requirement Specification |
Document identifying the requirements for the project |
| Weekly Reports |
Status reports to be issued weekly |
| Prototypes x 3 |
Three prototypes will be allowed for in the development. |
| Etc. |
|
Define
the
Functionality
Another technique is to define the functionality. This should not be either
a long or detailed process. Typically, depending on project size, the exercise
can be completed in a one hour to half-day workshop. A good technique is to
use a functional decomposition. If using a spreadsheet and a projector, a
scribe can create the scope as it is discussed. Remember to start all functionality
with a verb.
It is useful to do the functional decomposition in conjunction with a data
definition. If this is not possible, once the scope is discussed, it will
become reasonably clear what data is required.
The Project Manager can determine if there are any situations that need
to be clarified with the users, and finalise the scope definition. If for
example, in defining the functionality it becomes evident that considerable
information will need to be transferred from a legacy system, which is known
to be inaccurate, data cleansing can be factored into the scope.

Example
Functional
Decomposition
1.0 Capture License details
1.1 Set up companies
1.2 Set up products
1.3 Create licenses
1.4 Modify licenses
1.5 Delete licenses
2.0 Generate payments
2.1 Create payment report
2.2 Authorise payments
2.3 Notify accounts
Etc.
It can also be defined as a diagram:


Defining
the
Data
This approach is similar to functionality, and should be used
in conjunction with functionality. The process is likely to capture
what users expect to see in a system. The intention is not to
make the business users, data modellers. The intention is to
get the business users to verbalize their requirements for information
in a structured manner. Ask the users what are the people, places
and thing they want to keep track of. In this case, the focus
is on nouns.
This approach will not capture data that may be required to technically
make the system work. For example, it will not capture things
like transaction log files, archive files, SQL script files etc.
Post workshop, the Project Manager will need to sit with a data
modeller to sort out what else is required. The hardest part
is to stop doing a data model. Keep the focus on where the data
is to come from, and identify what is new, where the interfaces
are likely to be, is existing data suitable, is the data currently
captured etc.

Data
Definition
Example
| Name |
Description |
| Companies |
Details of the company including address, overseas offices, and up to
ten contacts |
| Licenses |
Licenses for all software and hardware used in the organisation. Include
contracts, correspondence, quotes and any other related documents. Does
not include manuals |
| Renewal dates |
Dates the license is due for renewal and the cost of the renewal. .
|
| Etc. |
|

Technical
Structure
Definition
This technique can be useful in defining scope where the project is focused
on infrastructure. It can also be useful in a situation where an existing
system is being modified. The output can be either a table, or a diagram.
A table might just list the components to be modified and the modification.
The structure diagram might identify the whole system and highlight which
components are being modified and how they are being modified. It may also
be appropriate to indicate the purpose of each component, however it will
probably be vague at this stage of development.

Example:
The 'outputs HTML' module takes information retrieved from the database
and inserts it into an .asp document for output to the server. It also updates
a transaction log with the database information and time of the output. If
an error occurs in retrieving data from the database, an error log is updated
and an error page sent to the server.
Example Technical Structure Table
| Component |
Description |
| Subsystem1 |
Handles all customer processing and interfaces to CMS (Customer Management
System). |
| Subsystem2 |
Carries out inquiries on billing systems (2) and combines data into
common format. Sorts data by date of payment. |
| Etc. |
|
Example Technical Structure Diagram


Other
Considerations
In documenting the scope of the project, also consider describing the project
boundaries, identifying the major business events, locations, divisions, functions
and processes affected by the project, as well as the groups of people impacted
both inside and outside the company. Consider also:
- Business processes that will be affected
- Business areas/units that will be affected
- Business locations that will be affected
- Business data that will be changed
- Business applications that will be changed
- Technologies that will be changed
All of these may have an impact on the project. For example if numerous locations
are to be effected, there may be issues of bandwidth, switching hardware,
travel and training, remote support etc.

Other
Work
The following is a list of work that may need to be specifically included
or excluded. Make sure it is clear if this is to be included, and that it
is documented. When we come to planning, it should be clear what needs to
be catered for in the plan:
- Preparation of training material
- Delivery of training
- Business Process documentation
- Business Process Re-engineering
- Rework
- Project management and administration
- Vendor management
- Security
- Disaster recovery plans
- Business continuity plans
- Provision and setup of equipment
- Software
- Communication
- Support after go-live
- Recruitment of permanent or contract staff
- Staff performance management and evaluation
- Hardware upgrade or purchase
- Hardware installation
- Data preparation for transfer
- System documentation
Summary
 |
Defining the scope is a neglected area in most projects. It is however the foundation on which the schedule, budget and resource plans are built. Get it wrong, and everything else will be wrong. If the scope definition does not run to a few pages, it is probably too short.
|
Take the time to workshop the scope with users. Make sure there is a shared understanding. Force the business to think through the project. Use a number of techniques to cross check. Finally, unless you get the scope right, the project will never be under control and scope creep will likely cause the project to be considered a failure.