PROJECT  PERFECT
                 Project Management Software
                         Information and White Papers for Project Managers

Menu
RSS News Feed Latest News.
Our Home Page
Home
Project Administrator main page
Project Administrator Software
   >Download 30 day trial
   >General Info
   >Cost Justification
   >FAQ for PA Buyers
   >Pricing
   >Buy Now
Method H Software Home Page
Method H ™ Software
   >General Info
   >Pricing
   >Buy Now
White Papers & Links
White Papers, Links & Free Stuff
   >White Paper Index
   >Student Information
   >Links
Consulting & Training Services
Consulting & Training
   >Consulting
   >PM Assessment
Project Management Blog
Make contact with us
Contact us
Search the site
Search
Contents of the site
Contents
Spread the word
Tell your friends about this page
Advise when we publish a white paper
Join the White Paper mailing list

VIP TO DO LISTS

VIP Task Manager s a client/server software for team collaboration and group task management.

Find out more information

VIP Organizer is a personal time and task management software to organize your agenda and improve your business productivity by using to do lists and checklists

Download a Trial Version

Find out more about VIP Software, click here

Project Management Methodology, templates and case studies
 
 
Home - White Paper Index

Earned Value Management

First published Aug 07

Tom Carlos (PMP)

Rating

Overview

Get Organised with Project Administirator Software There are “lucky” project managers whose projects were completed “on time” and “within budget.” But I am guessing they are in the minority. Everyone else has probably faced a situation where one of the following statements is true:

I am betting that the managers of these projects used analysis tools that are considered “two-dimensional.” “Budget” and “Actual” are the two dimensions. But in looking at a broader picture, there is a much needed third dimension- one that reflects “performance and efficiency.”

“Performance and efficiency” indicate whether or not we are actually completing the intended tasks and producing the expected project deliverables within the designated budget and schedule. To examine this concept, let’s look at the following case study.

Case Study

The Assumptions:

Initial Reports

Question for you

Would you agree with John’s assessment of the project?

If you answered “No” or “I do not have enough information to support that claim” you’re right on track. And to understand why that is the correct answer, let’s dig further into the problem.

What do we Know (for a fact)?

What do we NotKnow (to be true)?

To answer this question, John calls each programmer and gathers the following information:

Programmer

Budgeted Time

Actual time spent

Invoices Submitted

Percentage of all tasks completed

Bob

20 hours

15 hours

$1,500

60%

Sue

20 hours

25 hours

$2,500

75%

Roger

20 hours

5 hours

$500

10%

Mike

20 hours

30 hours

$3,000

50%

Jill

20 hours

15 hours

$1,500

80%

Total time and costs incurred

 

 

90 hours

 

$9,000

 

Table 1

Without going any further John can see the project has encountered a serious problem. Collectively, the programmers show 90 hours of work. However, no one programmer can make the claim that they have completed 90% of their assigned task (and final deliverable).

John scratches his head and is dumbfounded when it comes to understanding

(1) What has happened and

(2) What to do next.

So he asks an associate for help and she comes to the rescue.

Margie introduces John to a project management tool called Earned Value Management (EVM). In fact, she gives him an article that has the following definition:

Earned Value Management - The process of considering scope, schedule, and resources, measured against a project’s actual performance. It compares the planned amount of work to the completed tasks, to the projects’ cost, to determine if the cost, schedule, and work completed (thus far) are all in synch and in accordance with the plan. This analysis will show past performance and will estimate future efforts to complete the project (with the desired results).

The article provided by Margie also contains a table that shows all the terms, definitions, and formulas needed to conduct EVM analysis. Refer to Appendix 1.

At this point, John feels overwhelmed and has no idea how to apply the EVM terms and formulas to his project. So with Margie’s help, they slowly begin the analysis by defining the terms and plugging in the known figures.

Step 1 – The Starting Point Calculations

 

Symbol

Description

Formula

Explanation

PV

Planned Value

None

The estimated value of the work planned to be done thus far. In this case, the project’s PV is the estimated cost of $10,000 because we estimated the project would be completed within a week.

AC

Actual Costs

None

The total costs incurred to date, based on timesheets, invoices, other expenses, etc. In this case $9,000

EV

Earned Value

Sum of all (Task Budget * % Completed)

The estimated value of (intended) work completed thus far, as it relates to the expected deliverables.

Table 2

PV (Planned Value) and AC (Actual Cost) are easily derived. PV is based on what should have been completed thus far. For multi-period projects, it will seldom equal the full budget figure. The idea is to calculate a figure that represents “the amount of intended work; the work performed (thus far) in relationship to the assigned tasks.” In reality, EVM analysis will be done over several periods and the value for PV will be constantly changing.

To derive EV, multiply the budget figure by the percentage of all tasks completed (see Table 1). For example, Bob was given 20 hours to complete 4 subtasks. He estimated that 60% of the subtasks are completed. You multiply $2,000 by 60% and this gives a value of $1,200. So you can clearly see that Bob’s (real) work does not equal the actual cost of $1,500. As a result, Bob has fallen behind (in schedule and cost) based on this one calculation.

To calculate EV for the entire project, simply add the individual EV values for each programmer. Refer to Table 3.

Term

Value

Notes

PV

$10,000

Our budgeted figure

AC

$9,000

Total invoices submitted thus far

EV

$5,500

($2,000 * 60%) + ($2,000 * 75%) + ($2,000 * 10%) + ($2,000 * 50%) + ($2,000 * 80%)

Table 3

Again, we can see that the group as a whole has fallen behind on their work. They have submitted $9,000 as the cost but produced only $5,500 of (Earned) value. So at this point in time, the project appears to be $3,500 over budget. And we also know the project is behind schedule (because the tasks were not completed within the 1 week time frame).

Step 2 – The Performance Index Calculations

The Performance Index figures help us quantify efficiency. They are also used in subsequent EVM calculations.

Symbol

Description

Formula

Explanation

CPI

Cost Performance Index

EV/AC

I am (only) getting (blank) cents performance out of every $1 spent

SPI

Schedule Performance Index

EV/PV

I am only progressing at (blank) % of the rate originally planned

Table 4

By plugging in our known values for PV, AC, and EV, we can calculate CPI and SPI.

Term

Value

Notes

CPI

61.11%

Using (EV/AC); ($5,500 / $9,000)

SPI

55.0 %

Using (EV/PV); ($5,500 / $10,000)

 

 

Table 5

Based on these results, John can see that his team is working at an average of 61.11% performance efficiency. The 55% SPI index tells him that the project will most likely need another week for completion.

Step 3 – The Final Cost Estimates

John then asks Margie; “Based on this information can we calculate the project’s final cost?” So Margie rolls out the next set of terms and calculations.

Symbol

Description

Formula

Explanation

BAC

Budget At Completion

 

The original budget for the total job

EAC

Estimate At Completion

(See Appendix 1)

The amount "currently expected" for the total project cost

ETC

Estimate To Complete

EAC-AC

From this point on, how much MORE do you expect the cost will be to finish the job

VAC

Variance At Completion

BAC-EAC

How much over or under budget will the project come in at

CV

Cost Variance

(in dollars)

EV-AC

Negative is over budget, Positive is under budget

SV

Schedule Variance

(in dollars)

EV-PV

Negative is behind schedule, Positive is ahead of schedule

Table 6

BAC is the original budget total. For this project, it is $10,000.

Calculating a value for EAC can be tricky. There are four different methods for calculating EAC. Each method can yield a different result. Since Bob employs the principle of “conservatism” and wants the “worst case scenario” he uses the formula the yields the highest figure. (Refer to the Appendix 1 for all EAC formulas).

ETC is an easy calculation. This figure represents the additional costs from this point forward in order to finish the project.

Term

Value

Notes

BAC

$10,000

The original budget

EAC

$16,363

Using (BAC/CPI); [$10,000/.611]

ETC

$7,363

Using (EAC-AC); ($16,363 - $9,000)

VAC

- $6,363

Using (BAC-EAC); ($10,000 - $16,363)

CV

- $3,500

Using (EV-AC) with answer in dollars; $5,500 - $9,000

SV

- $4,500

Using (EV-PV) with answer in dollars; ($5500 - $10,000)

Table 7

At this point in time, the project appears to be $6,363 over budget (VAC). It will be next to impossible to hit the original target figure of $10,000. The current EAC value assumes that the programmers will continue working at the same pace.

The Cost (CV) and Schedule (SV) variances indicate that the project is “over budget” and “behind schedule.”

Step 4 – Overall Efficiency Ratings

John is shaking his head in disbelief. Not only is his project struggling to meet the original estimates, but he must now report the bad news at the next steering committee meeting. He knows that the management team will not be able to follow the calculations shown above. So he needs to simplify the reporting to three simply values.

Symbol

Description

Formula

Explanation

PE

Planned Earned

EV/BAC

Project % Complete (as it relates to time and deliverables)

PS

Percent Spent

AC/BAC

Project % Spent (as it relates to cost)

CSI

Cost Schedule Index

CPI * SPI

The overall efficiency rating. The further CSI is from 1.0, the project will have difficulties in recovering.

Table 8

Using the known values, John calculates PE, PS, and CSI.

Term

Value

Notes

PE

55%

Using (EV/BAC); ($5,500 / $10,000)

PS

90%

Using (AC/BAC); ($9,000 / $10,000)

CSI

.336

Using (CPI * SPI)

Table 9

The values for PE and PS do not surprise John. He has seen these figures before. But CSI is surprising. This value is far from “1” and indicates the seriousness of the project’s inefficiency.

The formulas provide a mathematical analysis of performance. Unfortunately, they cannot explain “why” the inefficiencies have occurred. For this, John will need to examine the work of each programmer in order to understand why they are all running over the allotted time for each task. Hopefully, he can correct the problems.

The other issue to consider is that the task lengths were severely underestimated. Interviews with the programmers may show that they in fact are working to the best of their ability. The problem may have occurred in the original project estimates.

Conclusion

There is much more to EVM than discussed in this article. But you are now aware of the third dimension of a project’s financial analysis. All three dimensions are key elements that must be considered when analyzing project performance.

Appendix 1 - The spreadsheet below summarises the situation with this project.

Appendix 2

EVM Terms, Definitions, and Calculations

 

Symbol

Description

Formula

Explanation

PV

Planned Value

 

(Also known as BCWS - Budgeted Cost of Work Scheduled) The estimated value of the work planned to be done thus far.

AC

Actual Costs

 

(Also known as ACWP – Actual Cost of Work Performed)The total costs incurred to date, based on timesheets, invoices, other expenses, etc

EV

Earned Value

Sum of all (Task Budget * % Completed)

(Also known as BCWP – Budgeted Cost of Work Planned)The estimated value of (intended) work completed thus far, as it relates to the expected deliverables

CPI

Cost Performance Index

EV/AC

I am (only) getting ____ cents performance out of every $1 spent

SPI

Schedule Performance Index

EV/PV

I am only progressing at ___% of the rate originally planned

BAC

Budget At Completion

 

The original budget for the total job

EAC

Estimate At Completion

Four options; see below.

The amount "currently expected" for the total project cost

EAC (#1)

 

BAC/CPI

Used if no variances from the BAC have occurred

EAC (#2)

 

AC + ETC

Used when original estimate is fundamentally flawed

EAC (#3)

 

AC + BAC - EV

Used when the current variances are atypical

EAC (#4)

 

AC + [(BAC-EV)/CPI]

Used when current variances are typical

ETC

Estimate To Complete

EAC-AC

From this point on, how much MORE do you expect the cost will be to finish the job

VAC

Variance At Completion

BAC-EAC

How much over or under budget will the project come in at

CV

Cost Variance

(in dollars)

EV-AC

Negative is over budget, Positive is under budget

SV

Schedule Variance

(in dollars)

EV-PV

Negative is behind schedule, Positive is ahead of schedule

PE

Planned Earned

EV/BAC

Project % Complete (as it relates to time and deliverables)

PS

Percent Spent

AC/BAC

Project % Spent (as it relates to cost)

CSI

Cost Schedule Index

CPI * SPI

The overall efficiency rating. The further CSI is from 1.0, the project will have difficulties in recovering.

About the Author

Tom Carlos has over 20 years of cumulative experience in business, technical, and training environments.  He is a Certified Project Management Professional (PMP) and member of the Sacramento Valley PMI Chapter. For other articles on similar subjects, you can visit www.carlosconsulting.com or contact him at tom@carlosconsulting.com.

Project Perfect

Project Perfect is a project management software consulting and training organisation based in Sydney Australia. Their focus is to provide creative yet pragmatic solutions to Project Management issues.

Project Perfect sell “Project Administrator” software, which is a tool to assist organisations better manage project risks, issues, budgets, scope, documentation planning and scheduling. They also created a technique for gathering requirements called “Method H” ä , and sell software to support the technique. For more information on Project tools or Project Management visit www.projectperfect.com.au

 

To date, 27 people have rated this article. The average rating is 4.63 - Add your rating. Just select a rating and click the button. No other information required.

Only one rating per person is allowed.

 

Earned Value Management
1 2 3 4 5

Return to the top