Project Planning

Previous

Produce Project Charter

Next
Present a Project Charter for approval. The Project Charter is the initial business justification for the project to begin.
  • Purpose of the project
  • High Level Scope
  • Timeline
  • Resource Requirements
  • Roles and Responsibilities
  • Risk Assessment
  • Costs and Benefits
    1. Complete the template for Project Charter
    2. Submit to the Sponsor for Approval
  • Project Charter ready for approval

This activity is largely about pulling together the work completed in the phase. The final document is substantially a collection of attachments that have been created up to this point. As you work through each component, previously completed components may change so you need to revisit each document to ensure it is correct at the final point.

At this stage, cost may still be out by 100%. The potential variation should be identified in the Project Charter. For example if the project is straight forward, and is similar to many others, the potential variation may be small - say 20%. If the project is addressing a new area (new technology, new functionality), it may be 100% or even more in some cases.

The financial's of the Project Charter may need input from your Financial area to ensure it meets the specific requirements of the organisation. For example, you will need to ensure you use an inflation rate that mirrors other estimates in the company when calculation NPV (Net Present Value)

There are two related documents:

  • The Project Management Plan identifies how the project will be managed. It describes the mechanics of the project management process. The PMP is produced later in the phase.
  • The Schedule shows the activities, times, sequencing and resources to be applied to the project. It exists in draft but will be refined later in the phase.
Project Charter Document to assimilate all the information you need to justify the project into one document.
Nil  

Return to the top