Contract Bid and Technology Proposal
Evaluation in Project Management |
First published
Feb 10
|
Eric Tse
|
Rating |
|
|
Abstract
This
white paper focuses on the management perspective of different
project proposal evaluation methodologies in the procurement
processes. Our goal is to introduce in details as to how
proposal evaluations take place in procurement management
processes using both literatures and industrial experience.
We list out building blocks of the process, types of models
and methodologies, evaluate and unified different processes
and models. We also highlight insights on what you can
do to win the contracts. The references are mostly from
Information Technology industry and academia literature.
The in depth technical, environmental evaluation attributes
will only be highlighted in this paper. The details would
not be addressed in this paper.

Background
What is a technology proposal evaluation? This is too
broad just to write one paper and describe all the varieties.
In short, I would like to highlight some problem statements
we can see in our real life?
For example,
- Which consulting companies we should choose to set
up our system solutions?
- Which vendor products we should purchase for a particular
purpose and why?
- What is the better software and application architecture
between A and B?
- What is a better solution architecture and why?
- What is a better OS with better hardware with better
DBMS in better server farms to host this mission critical
application?
- Is it still a good architecture/technology after disasters/pitfalls
happened? (Out of scope of this paper)
Although there are many technical details involved in
making such decisions, we focus on what managers should
do to make those decisions. Managers make such decision
heavily based on technical advice from architects and
independent consultants. What technical attributes an
architect should consider will be discussed in another
paper.

How bidding and proposal evaluation fits in the procurement
process?
Above is the procurement process in the Project Management
Body of Knowledge (PMBOK) 4 th version [1]. We are somewhere
between evaluation plan procurements and conduct procurements
and how evaluation fits in the process.
What are the Building Blocks?
1) Input and Output:
- Input -> We would like to buy something or to do
something
- Output -> We choose/buy vendor A/company A to do
this projects.

2) Involving Parties
Concept of Stakeholder, people related to the project
[2]. I will categories how the decision was made based
on three forces. Following is the “Three Parties Model”.
- The people who pay the money (financial and political
perspective)
- The people who use the technology (usage and business
perspective)
- The people who build and manage the technology (technology
development, project and operation management)
- Independent evaluation team (neutral and external,
not counted in the three parties)
The people who pay the money have the biggest power.
Cost involves the cost of building the solution, and also
the cost of managing the solution in the long term. The
Sponsors won't pay the money unless they have good inputs
from the other parties.
The ultimate driver of the technology is the business
user. However the feedback from users is benefits driven
and not cost driven. Their requirements may end up costing
the Sponsors a lot of money, as well as costing developers
and administrators lots of time and effort.

3) Types of Evaluation Tools and Methods
- Questionnaires, prototype, simulation, analytical,
data collection, data analysis, hypothesis, force field
analysis, and hierarchy decision process, or weighted
average metrics, iterative feedback

4) Principles
Cost and benefits (ROI) [2]
- Cost - how much I need to pay
- Benefits
- Make money
- Save money
- Look good
- Feel good

5) Most simple high-level steps
- Develop criteria and define requirement
- Request for proposals (open for bids)
- Evaluation and selections
- Resulting contract clauses, terms and conditions

6) Bidder Instructions and Guidelines
- Bidder Instructions and Information
- Proposal requirements
- Evaluation and selection criteria.
- Additional requirements
- Resulting contract clauses
- Appendix
Bidder Instructions and Guidelines
(Details from Federal Government Agencies)
Bidder Instructions
and Information |
- Scope of
requirement
- Requirement categories (mandatory,
rated, information)
- Revision departmental name
- Standard instructions clauses and
conditions
- Priority of document for request
for proposal (request for proposal, SOW (Statement
of Work), pricing tables, resulting contract
clauses, hardware, licensed software, contractor
intellectual property, general conditions, long
form, security requirements checklist)
- Bid receiving and proposal delivery
address,
- Previous communication between government
and bidder. (Should be based on this document)
- Enquires – solicitation stage (bid
solicitation must be directed only to contracting
authority)
- Amendments to request for proposal
- Amendments to bidder proposal,
- Ownerships of proposals
- Rights of Clients (accept any proposal,
reject proposals, cancel requirement, reissue
requirement, request clarification, accept
or waive, minor mistakes error with no change in
the price quoted)
- Proposal and pre-award costs
- Procurement business number
- Joint venture proposals
- Bidders responsibilities
- Approval and funding
- Reference to Information not contained
in the proposal (websites address, technical
manuals)
|
Proposal requirements |
- Security
requirements (security clearance)
- Presentation and structure of proposals,
(financial proposal, terms and conditions,
technical proposal section, supporting information)
- Contents of proposal – general (legal
name and status, bidder contact, content, identification
of confidential information)
- Validity of proposal
- Technical proposal (article by article
response to the SOW, information SOW, requirements,
technical brochures and supporting documents,
pre-printed bidder documentation)
- Financial proposal, (Tax, proposed
pricing, firm requirement, optional requirement,
financial capability, past history financial
statements, short term financing)
- Terms and conditions proposal (validity
of proposal, article by article response to
section RFP, certifications and signed pages, article
by article response of RFP. comply, do not
comply, not applicable)
- Contract options
- Reference to existing document
- Bidder‘s representative
- Sole bid – price support (Current
published price, copies of paid invoices of
good and services, a price breakdown, price or rate
certifications, other supporting documentation)
|
Evaluation and selection
criteria |
- Evaluation
team (independent consultant, or government
resource, contact reference)
- Information on capabilities (review
of financial status, ensure proper performance)
- Evaluation and selection methodology
(varies)
- Clarifications.
|
Additional requirements |
- Applicable
laws
- Training documentation
- Non-disclosure agreement
- Authority to grant license
- Contractor program for employment
equity (social welfare)
|
Resulting contract clauses |
- Security
requirement
- Revision of departmental name
- Standard clauses and conditions
- Conditions
- Priority of documents
- Requirement
- Contract period
- Optional requirements
- Software licensing
- Shrink wrap licenses
- Delivery
- Redesign or reorganization of client
- Authorities
- Agency restricting
- Contract's representative
- Basis of payment
- Basis of payment – options
- Professional services
- Time verification
- Liability for changes
- Time verification
- Liability for changes
- Maintenance price protection – after
option periods
- Goods and services tax or harmonized
sales and tax
- Inspection and acceptance
- Site regulations
- Government service contract payments
- Foreign nationals (local company)
- Foreign nationals (foreign company)
- Method of payment
- Termination/refund to Company
- Invoicing instructions
- Applicable laws
- Federal contractor's program for
employment equity – certification
- International sanctions
- Modification of general conditions
9601 – Long form
- Limitation of liability
- Intellectual property right infringement
- Alternative dispute resolution
|
Appendix |
- SOW, pricing
tables, proof of proposal testing, security
requirements checklist, definitions
|
Request for Proposal
A request for proposal (referred to as RFP) is an invitation
for suppliers, often through a bidding process, to submit
a proposal on a specific commodity or service.
Principles, Request for Proposal
- Understand request
- Financial proposals
- Technical proposals
- Article to article response (compliance, non compliance,
not applicable)
- Terms and conditions proposals
- Proven financial and technical track record

RFP Examples
Request for Proposal Example 1 (Another Canadian
University)
- Purpose of the RFP
- Company background (Some statistical
information of users)
- Goal of having a solution at the organization.
(Vision)
- Key objectives (disclosed evaluation
criteria) set of high level characteristics, such as
improve administration, improve security, minimize complexity,
increase efficiency, improve overall management, improve
compliance, leverage standards, position for the future,
enable integration.
- Scope related to other external components
with other enterprise
- Acceptance Test (proof of concept). If
award contract, (insurance, employee liability insurance)
- Function requirement/specification

Request for Proposal Example 2 (Canadian University)
- Company profile.
- Understanding client objectives. (Vision)
- Company meets client objective (security
best practice and approach and methodology, and proven
track record)
- Offer a property methodology, successful
IDM solution and team of high skilled professionals.
- Approach to project management

Request for Proposal Example 3 (US State Library)
- Demonstration of understanding of scope
of project and purposes, address vendor strategy to
meet each requirement, functionality exists in vendor's
system, vendor strategy for maintaining and supporting
the system, describe the resources currently available
and to be dedicated to ongoing support for this software
- Link to demonstrate both compliant search
target
- Demonstration of the system, (bidder
conference)

Different evaluation methodologies and comparison
Simplistic Industrial Models
Canadian Federal Government Agency (Evaluation
and selection methodology)
- Phase 1: Terms and condition, financial and technical
proposal, evaluation of mandatory requirements.
- Phase 2: Evaluation against the rated requirements.
- Phase 3: Financial Evaluation
- Phase 4: Ranking of bids – both technical merits and
price based on highest combined rating of technical
merit and price, where technical merits is 25% and price
is 75% of total points. Lowest technical compliance
proposal will be chosen.
- Phase 5: Proof of proposal – test phase (10 working
days), evaluation will document the result, determine
the proposed solution meet mandatory requirement of
RFP.
- Phase 6: Contractor selection – (met all mandatory
requirement, overall passed mark of the rated criteria,
overall combination price and technical merit, has passed
the POC test), would granted an award.

Canadian University (Evaluation and
selection methodology)
- Initial selection: Vendors should summarize how each
component or relevant service in the product family
addresses the requirements outline.
- Selected few submissions: Technical Q & A session
-> final check lists preferred vendor selection (metrics),
(features and performance (25%), reputation and viability
(25%), total cost of ownership (50%).

Complex Theoretical Models and processes
US State Library , “Technical evaluation
methodology for RFP demonstration Systems and RFP written
responses. University of North Texas” [3]


Legal Software: extension the ISO 14598
evaluation process with a novel evaluation framework - “ A
process for evaluating legal knowledge-based systems based
upon the Context Criteria Contingency-guidelines Framework” (complex)

- Four quadrant model
- Verification criteria: Canvas aspects of
technology ‘in the small' i.e. at the program rather
than the infrastructure level
- Credibility and acceptability of a system
to people ‘in the small' i.e. at the individual rather
than organizational level.
- Criteria from this quadrant are concerned
with aspects of technology ‘in the large' or technical
issues beyond the immediate program or system level
- Mainly associated with people ‘in the
large' i.e. beyond the considerations of an individual,
however criteria associated with personal impacts have
been included here for convenience. Criteria canvas
the impact of the system upon its environment, including
tasks, people, the parent organization and beyond. Personal
impact criteria include effects on job satisfaction,
personal productivity, motivation and morale, health,
welfare and safety including stress exposure and impacts
upon privacy and personal ethics. Changes in working
conditions, participation and involvement, autonomy
and social interaction can also be measured. Social
factors, ethics and integrity, can also be canvassed
- A ‘contingency' is the possibility that
something may occur in the future. A contingency-guideline'
is a suggestion on how to deal with it.


Educational Applications of State Organization: C
ollaborative process for evaluating new educational technologies
- Emphasize a pilot and incremental and iterative feedback
- There is a lot of time between pilot and the decision
making
- Better and more through evaluation, but takes more
time at the beginning

C ollaborative Hierarchical
fuzzy TOPSIS Model for selection among logistics
information technologies [6]
- Introduce fuzziness and multi-facet-ness
- Views the problem with m alternatives as a geometric
system with m points in the n-dimensional space
- Defines an index called similarity (or relative closeness)
to the positive-ideal solution and the remoteness from
the negative-ideal solution.




Discussion and Tips
- When we observe the typical outcomes of technology
management and investment appraisal and technology there
is still a wide variation in how evaluation of technology
is carried out and the results that are achieved. What
has been learnt so far however is that as organizational
goals and circumstances change, so do/should the appraisal
process. [7]
- The process and nature of evaluating and making technology
decisions requires continual experience and applied
knowledge in order to succeed. I fear that there is
a real risk of trying to do too much, to over-analyse,
to over-evaluate; thereby intrinsically increasing complexity
and widening choice and uncertainty. [7]
- Technical evaluation can be very different in different
situations. For example Software/application (architecture),
solution systems selection, vendor selection, planned
(before using) or unplanned (disasters), bidder's evaluation,
different nature of the problem may turn out to have
totally different evaluation models.
- There are at least three types of stakeholders driving
the evaluation. The people who pay the money, people
who develop and manage the operations, and people who
use the systems. They have conflicting goals although
eventually they are subject to financial and political
perspectives.
- The major consideration for a bid is financial. Don't
think technical merits are that important. However there
are limitations of any industrial evaluation process
that over emphasize the short term financial benefits,
and didn't consider enough the long-term financial benefits,
which are usually related to technical merits.
- If you want to win a contract, there is an implication
that you can squeeze the cost by trading off some of
the technical merits.
- In order to save time and effort in considering everything,
companies request a proven track record, and the financial
status of the bidding contractors. This serves as a
cognitive shortcut for the buyers to avoid spending
effort evaluating the proposals.
- In many industrial experiences, the evaluation process
is relatively short. With limited time and resource
budget, it is hard to have a thorough evaluation. No
one has the money to cover the cost in technical evaluation.
All the evaluation methods used are relatively lightweight
and only consider verification, credibility and acceptability
criteria. The infrastructure and impact criteria can
only be fulfilled after a procurement decision has been
made.
- From some of the federally funded, large scale, or
academia research based projects (mostly in the US),
the evaluation process can be quite long and well funded.
It emphasizes building of a pilot, phase based, incremental
and iterative and collaborative methodology. It ensures
all four quadrants of criteria and contingency guidelines
would be considered before the contract is granted.
- There is a paradox between having a finer evaluation
before or after the contract is awarded. On one hand,
having a better evaluation at the beginning may save
us from making the wrong architectural decision at the
end and cost us tremendous money to fix or change the
solutions. On the other hand, we may want to only do
what is absolutely necessary at the beginning. Things
may change during the implementation and doing too much
at the beginning may introduce risks, hinder future
decisions and be redundant.
- We may be able to put the evaluation activities in
an “onion model”. In the core of the onion we have basic
analytical evaluation and definition of evaluation and
criteria. The next layer would include verification,
credibility and acceptability; the outermost layer would
include infrastructure, impact, pilot, models, iteration,
collaboration, fuzziness and multi-facet-ness. The more
outer the layer, the better quality and higher cost
of the evaluation techniques. Enterprise can choose
the sophistication of the evaluation of the process
based on their needs and available budget. Also different
layers of evaluation can be put into different phase
of the projects, some before the bid awarded - some
after awarded.

Conclusion
Contract bid and technology proposal evaluation impacts
the business decision of a project, i.e. to open a project.
Choosing the right methodologies to make a correct decision
is important to the buyer. Hitting the important points
and address the needs with the right solution design at
a reasonable cost is important to the seller. Bear in
mind a technology proposal evaluation is not technical.
Technical evaluation is only a subset of the whole evaluation.
It is driven by financial and organizational political
factors. Neglecting thorough technical analysis and technical
merits may end up costing you more and make your business
look very bad at the end.
Reference
[1] Project Management Institute. (2008). A Guide to
the Project Management Body of Knowledge (PMBOK Guide) – Fourth
Edition.
[2] Len Bass, Paul Clements, Rick Kazman, Linda Northrop,
Amy Zaremski. (1997). Recommended Best Industrial Practice
for Software Architecture Evaluation
[3] William E, Moen, Kathleen Murray, Irene Lopatovska.
(2003). Technical evaluation methodology for RFP demonstration
systems and RFP written responses. University of North
Texas,
[4] Maria Jean J. Hall , Richard Hall
, John Zeleznikow . (2003). A process for evaluating legal
knowledge-based systems based upon the Context Criteria
Contingency-guidelines Framework
[5] Greta Kelly. ( 2008). collaborative process for evaluating
new educational technologies
[6] Cengiz Kahraman, Nu¨ fer Yasin Ates¸, Sezi
C¸ evik, Murat Gu¨lbay and S. Ayc¸a Erdog?an
( 2003) Hierarchical fuzzy TOPSIS model for selection
among logistics information technologies
[7] Amir M. Sharif. (2008). Paralysis by analysis? The
dilemma of choice and the risks of technology evaluation
The Author
Eric Tse is an international recognized expert/consultant
in Enterprise Access and Identity Management Architecture
Design and Implementation. He has been working with international
renowned experts in information technology in many prestigious
companies. He also pursues research interests in project
management, financial models, application/enterprise/solution
architectures, compilation technology and philosophy of
science.

To date,
3 people have rated this article. The average rating is
5.00 - Add your rating. Just select a rating and click the
button. No other information required.
Only one rating per person is allowed.
|