Overview
Market driversIn recent times, most of us know that each IT company competes heavily with the others in the market. All the companies deliver systems that are claimed to be bug free, of high quality, reliability, scalability, etc. The truth is that there are no products that are bug free and we can only try to eliminate the bugs from the product by following worthwhile processes and methodologies. By doing this, we ensure that the product is stable enough and sanity checked. These are the key factors that determine the success of a project. Just by adhering to the project deadlines or completing them well ahead of schedule without any proper process in place will result in rework that will cost the customers a lot more. The key to any business is the customer. It is better to build a product that has a very low percentage of bugs that can be discovered in unusual environments or impossible scenarios. This is the corner stone of quality, success and repeat business
Problem developmentWhenever a person architects a project, develops a module, he or she takes great care in ensuring that his or her code is the best. If you find fault in their work, some will get offended while others might take it in their stride. The artifact also undergoes proper review by peers and is passed on to the next stage. What is the net result? We still have bugs that can be found. The reasons could primarily be human error which is unavoidable. So, how do we mitigate this problem? As a project manager, you are committed to delivering a robust product.
A generic introduction to the solutionOne solution that I have been exercising in my projects is the Pareto principle which is the 80-20 principle. Pareto advocates that 20% of the causes in your project will resolve 80% of the problems. Though there are many ways to achieve this, I personally feel that implementing a Pareto Chart results in considerable improvement. The manager must sit with his team once a month and brainstorm the issues. The brainstorming can happen from the requirement phase to the implementation phase. As you know, defects are captured in all the phases. The manager should have collated information from all types of review feedback. He can fetch them from any type of tool that he may use in the project like Rational Clear Quest, Test Manager or in an Excel sheet. The entry criterions are the cumulative review feedback, resources in the project and a conference room. Every review feedback must be discussed in depth. For each review comment, the root cause analysis must be done by the team and they must come up with a particular cause of the problem. An example for a root cause could be “Inadequate self review” while the review comment discussed could be “Array out of bound exception”. All of the defects - Schedule or effort variance if any & defects from review report must be discussed in a similar manner and categorized into various causes. They should be grouped by the cause. For all the categories of the root causes identified, preventive action must be taken during the session. This is the most important step during the brainstorming session. Just identifying the root cause will not help in resolving the issue. The preventive measure arrived at and understood will serve in ensuring that these errors will be averted in future. The main entry criteria for coming up with Pareto Chart is the root cause analysis and preventive actions.
Benefits
ExamplesLet me narrate how I draw the Pareto Chart using the template that I follow for my projects. Open up an Excel sheet and enter the details below. Causal analysis must be done every month to perform the health check for your project. The frequency is not very stringent as for the projects that follow. Agile will have a shorter delivery durations and hence the causal analysis can be done every week or even lesser based on the project needs. Make an inventory of all the defects that are reported in the review documents. After brainstorming with the team, you will need to fill in the cause of the defect and come up with a preventive action. See Figure 1 below.
Figure 1: Causal analysis template Examples of causes of defect can be
The Figure 2 depicts a sample causal analysis and its preventive action mentioned.
Figure 2: Causal analysis and preventive action example Once you are ready with this sheet, we can go ahead in identifying the top 5 defects in the project for a given month.
Figure 3: Categories and No. of occurrences template In Figure 3, you can see the categories of defects column and defects identified column. From figure 1, all the categories identified should come to the Category column in Figure 2. The no. of defects that falls under each category must be the values in the Defects column. Sample values in the figure 2 can be
Figure 4: Categories and No. of occurrences example After ordering the categories and their number of occurrences, Figure 5 must be drawn. This will help in ranking the categories based on the frequency of occurrence. Calculate the percentage and the cumulative percentage. For example, the percentage of “Inadequate self review” is (42/92)*100 = 45.65%. Similarly we need to calculate for all the other categories.
Figure 5: Rank the no. of occurrences in descending order Cumulative percentage will be the sum of the previous cumulative percentage and adjacent percentage. Figure 6 represents the example.
Figure 6: Rank the no. of occurrences in descending order Now a Pareto chart is drawn as below. Pareto chart can be drawn by using a combination chart. To make a combination column-line chart, select a standard clustered column chart in the first step of the Chart Wizard. Press the Finish button to skip through the rest of the Wizard, to generate the bar chart. To create a line chart showing the percentage, create another series and set the data values. If you want to combine the bar (Pareto) chart with a series graphed as a line, just graph both series as bars and then right click on the data series that you want as a line and select “Chart Type” and change it to a line.
Figure 7: Pareto Chart You should not stop here. You have now identified the top 20% of causes that create 80% of problems in your project. In other words, you have indicated that you need to immediately address these top issues and implement the preventive action. When the next monthly review happens, these errors must be eliminated or at least their percentage must be low. This means that you have actually improved by making your team consciously follow and implement the preventive actions discussed during the brainstorm meeting. Hence eventually you will get rid of these errors in your project during the initial phases itself.
|
|||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|