|
Project Managing a New
Boat |
First published Dec
09
|
Neville Turbit |
Rating |
|
|
Overview
I have always been a sailing boat rather than a power boat type
of person. I have owned a number of yachts, the last of which
was an S&S 30. Unfortunately the family were not into sailing.
As the years went on the yacht just sat on a mooring and more
time was spent maintaining it than using it. Eventually it all
got too hard and I sold the boat a few years ago. It is not an
uncommon situation. I have spoken to many former yacht owners
who found the same thing.
Living near Sydney Harbour and not having a boat seemed such
a waste. I had never had much to do with powerboats but decided
I would buy one and see if the family were keen enough to make
use of it. We discussed it and they were enthusiastic.
Why am I telling you this? Being a Project Manager, I treated
it as a project. As I near completion, I want to share with you
my approach and some of the lessons I learned by using project
management outside the conventional business area. In some areas,
it was not pretty.

Phase One - Planning and Requirements
I didn't start out to run it as a project. It just sort of happened.
When I had talked it over with the family, they seemed keen so
I sat down to work out what I needed to do. As I said I had always
had sailboats so power was a new experience.
Time to go into information gathering mode. I did hours of research.
Talked to all sorts of people who would provide information and
began to get a feel for the sort of boat I wanted. After running
it past a few people, I came up with a list of about 20 requirements.
Some financial analysis resulted in a budget. The budget had
to take into account, not only the purchase, but other factors
as well. For example the cost of putting down a mooring and buying
a dinghy to use as a tender. It had to cover insurance and registration.
In the end the budget had about a dozen major items of expenditure
in addition to the boat. That was the first surprise. Because
I had a fixed budget, the cost of all the associated expenses
limited the amount I could spend on a boat.
Probably the most significant requirement was that I was prepared
to sacrifice age for size. In other words, I was not looking
for a new boat. I was looking to buy an older and bigger boat
rather than a newer smaller boat. Little did I know where that
was about to lead me.
Other things like the style of boat, and the size were reasonably
clear. I was looking in the 26 to 28 foot range; fibreglass;
shaft drive; roomy cockpit for taking a group of people out on
daytrips. I had a preference for diesel over petrol but the engines
had to be low hours as I was discovering that petrol engines
only last about 1,000 to 1,500 hours. I was looking at something
built around 1980.
So far so good. I had made a list of around 10 models from that
period that fitted the requirements. The next phase was to find
the boat and negotiate a price.

Phase Two - Search and Buy
Phase two was not time bound. I was happy to spend months or
even a year or two to find the right boat. I circulated my requirements
to a number of brokers and looked over a few boats. Nothing jumped
out but there were a few potentially interesting ones around.
Having a list of requirements made it much easier. I was able
to tick off the requirements and at the end of each inspection,
see how well the requirements were met. In fact telephone calls
often saved a trip to look at the boat. The fit was not near
enough to consider.
As I looked at more boats, I started to learn more about particular
models and could refine requirements even further. There was
no shortage of boats on the market and during business trips
I tried to find time to look at boats in other locations. Just
hanging around marinas and talking with boat owners proved enlightening.
One boat came up that was outside the requirements in some ways,
but also exceeded them in others. It was a Cresta 34 - 6 feet
longer than I was looking for but 10 years older. The price was
slightly above the target range so if I decided to consider this
boat, there would have to be a justification put forward to extend
the budget. Still thinking like a Project Manager.

The Cresta 34 for sale.
On the positive side it had two relatively new engines although
they were Chevy V8 petrol. I would prefer diesel but had not
ruled out petrol. It was a few hours drive from home but we
decided to look at it.
The key stakeholder was impressed. No need to explain who
the key stakeholder was to any married man. The only problem
was she didn't like the colour. It was best described as battleship
gray. Still a coat of paint could fix that as it was only
the deck and cockpit area.

Interior had lots of wood panelling and but
was in good condition
Condition was not great as it had little use over the last
four years according to the broker. Paint was peeling. There
was some rot in the cabin, and it generally looked tired.
On the positive side, the motors were relatively new and it
had an enormous cockpit area. Even had a 240 volt generator
and such luxuries as a TV and Fridge.
Time for some risk management:
- What if there were unforseen problems and it turns out
to be a lemon? Mitigation . Find a good
boat surveyor who can do a thorough inspection.
- What if I buy it and cannot get a mooring for months?
Mitigation . Put my name down for a mooring
where there is a relatively short waiting list.
- What if the brand Cresta has a reputation as a floating
financial black hole?
Mitigation . Talk to other brokers and find
out about the brand. As it turned out Cresta was a well respected
brand and still make a limited range of boats.

Haggling
To avoid a change request to the bank manager, we started
negotiation by offering a figure close to the top of the target
budget range. It was well under the asking price but no harm
in trying. As expected it was rejected but we had opened negotiations.
Over the next few months offers and counter offers continued.
A variation was definitely likely so we started to weigh
up the costs and benefits of changing the target range. The
key stakeholder "just liked it". I was a little more pragmatic
and started estimating the benefits.
If the engines lasted longer, the eventual cost of these
engines could be amortised over a longer period. Say replacement
cost of engines was $30k and they lasted 10 years, the cost
was $3k per year. Being almost new, I could probably gain
an extra 2 or 3 years which equated to $6k to $9k over an
average boat in the target range with 3 or 4 year old engines.
Most of the interior was timber which meant I could do a
lot of the work myself. Had it been a newer boat with lots
of moulded fibreglass it would have been beyond my skills
to fix up the interior. Estimated saving $3k to $5k. In total
I came up with about $12k to $15k of quantifiable benefits.
There were other benefits such as the ability to cater for
additional people and the comfort of the additional space.
The generator was also a bonus as it would make use of power
tools an option to carry out repairs. The boat was to live
on a swing mooring rather than at a marina so there was no
shore power available. The cost of a marina berth was not
in the budget.

Inspection
After a few months of negotiation we reached a figure that
was acceptable. Final agreement was subject to an inspection
of the boat.
At this stage I took the boat for a run and there were a
few minor problems but it certainly met our requirements.
We gave it a good run under full throttle and the engines
performed without a problem. A few of the electrics did not
work but that was consistent with a boat that had hardly left
the mooring over the last few years.
Being an old boat, I expected there would be lots of work
identified and the intention was to negotiate the completion
of essential work as part of the purchase price.
I was not disappointed. The survey came up with around 50
items in need of maintenance or repair. Stage two of the negotiation
involved agreeing what would be repaired as part of the purchase
price. Another period of haggling took place and eventually
agreement was reached. Repairs were carried out.
In retrospect, there was a problem in my project management
approach at this stage. It related to quality. I should have
spent more time and effort to check the quality of the repairs.
The boat was a few hours away and I relied too much on the
broker to manage repairs. That was a mistake. I should have
had the surveyor who did the inspection revisit the boat and
check repairs. It would have been expensive but would have
been worthwhile. This was not the only quality planning mistake
I made. I will come to the other major one later in the white
paper.

Purchase and Delivery
The final step was to part company with the money and bring
it to Sydney. A temporary mooring was organised as my permanent
mooring was still a month or two away and we arranged a friend
to drive us to the boat one weekend so we could bring it back.
Just as we arrived at the marina, we had a phone call from
a mechanic who had serviced the Onan petrol generator. He
told us there was a problem with an electrical cut-out switch
and the generator might not work properly. The petrol engine
was fine but the generator was cutting out. Nice to know just
as you are about to leave. It was not essential. Just meant
we could not make a coffee on the way down as we had no power
for the stove.
Another surprise was that when we went to start the motor,
one motor kept cutting out. A call to the broker and a mechanic
arrived to point out that we had run out of petrol in spite
of the gauge showing over a quarter full. We topped up the
tank with enough fuel from a can to get us to another marina
where we could fill up. The broker had told us it used around
15 to 20 litres per hour at 7 knots. If you wanted to go faster
where the boat planed, or lifted out of the water it was about
40 litres per hour. At planning speed (20 knots) we estimated
the time to Sydney would be around 6 hours.
The tank held 400 litres but the pickup for the fuel tank
was not at the bottom of the tank. There was room at the bottom
for sediment and any water that may get into the tank over
the years. We based our trip on being able to use 350 litres
which gave us a safety margin of 100 litres. The tanks were
filled and we settled down for the night planning to leave
early the next day. Good project management - or so we thought.

The Trip
About half way down the coast, we looked at the fuel gauge
to find it was between three quarters and half. Knowing that
a quarter means it was empty, we were getting a little concerned.
It continued to drop more than we would have liked. If it
was accurate, we were burning closer to 60 litres per hour.
Was the gauge wrong, or did the broker stretch the truth?
We had an issue. Options were to keep going and hope the
gauge was wrong, or reduce speed to 7 knots and hope the cruising
consumption was accurate. I tried to see if the tank could
be checked with a dipstick but there was no access without
much removal of panels. We decided to cut the speed.
By the time we were approaching the mooring after adding
a few hours to the trip, the gauge was on a quarter. A safety
feature was that the fuel pickup for one engine is lower than
the other. One engine will stop before the other so if you
do run out of fuel, you get a warning when one stops. You
have the other engine to get to a safe anchorage or a refuelling
point. One engine stopped about 50 metres from the mooring.
Aside from the fuel issue and the generator we were happy
with the boat. Phase two was complete. Now to move on to the
big phase which was to get the boat up to a level of reliability
and condition that would ensure we could enjoy it.

Phase Three - Maintenance and Repair
Having purchased the boat, I asked the broker if the previous
owner would agree to a visit or even a phone call. I wanted
to meet him so that I could get to know some of the quirks
of the boat, and understand what modifications the owner was
aware of, or had done. The owner refused to talk with me or
even provide a telephone number. When I have sold boats, I
have spent up to a full day with the new owner going over
every inch of the boat to pass on any information that might
be useful. This meant that planning work on the boat was more
difficult.
I started with the work identified during the inspection.
In true project management style I created six priority levels
and then allocated each piece of work a priority. Next I did
a thorough inspection myself and identified any other work
which was also prioritised. Although we had brought the boat
to Sydney, I went out a few more times looking for other problems
and found a few. Next was to look at essential modifications,
additions and upgrades and prioritise them.
One of my favourites was on the flybridge. For non boating
types, the flybridge is the upstairs section where you steer
the boat. The boat had a wheel and controls in the cabin and
a wheel and controls on the flybridge. It could be steered
from either position.
As you can imagine, the flybridge is not a very stable platform.
Moving around you are subject to considerable rocking as you
go over waves. You tend to hang onto rails and get into a
seat as quickly as possible. The flybridge had a rail which
was around 50 cm high at the front but sloped down to around
15 cm at the rear. If you moved towards the rear of the flybridge,
not only was there no rail to hang on to. There was a rail
at ankle height to trip you as you fell off the back. It had
to go.
After a week or two the scope was finished. There was a list
of 130 items to attend to. Some were an hour or two and others
a few days work. All were prioritised and grouped into related
activities e.g. electrical or carpentry work. I put some time
estimates together and created a schedule. I also made allowance
for work that had not been identified, and work that would
be more complicated than I expected.
I also did a cost estimate and came up with a budget. As
most of the work was to be done on weekends, I did an estimate
that said there was about a year of known work to be completed.
I decided to split it into two sub-phases. I would work weekends
as one sub-phase, but plan to take two to three weeks to undertake
major refurbishment at the end of that period. Get all the
minor or urgent work out of the way on weekends, and then
spend a solid chunk of time to do things like repainting.
It was much more efficient to repaint over consecutive days
rather than come back to it every weekend. We had a plan.
What were the risks?
- The biggest risk was that I would hit a problem that would
exceed any budget allocated. As I could not come up with
a mitigation strategy for that, I had to accept the risk.
- The second risk was that I would not be able to find the
two or three weeks I needed to do the major refurbishment.
Mitigation. Review the two sub-phases and
ensure there are no work items in the refurbishment phase
that will stop me using the boat. At least if it is delayed,
I can continue to use the boat when I have time available.
- The third major risk was that I would not have the skills,
and could not easily locate someone with the skills to undertake
some of the work. As I said, I knew my way around sailboats
but not power boats. If I wanted something relating to power
boats, where did I go?
Mitigation. I started researching companies
and people who fixed things on boats. There is a lot of information
available on the web, and by using forums, you can get an
idea of satisfaction levels with particular people or companies.
I also tapped into my boating network to find recommended
providers.

Generator
As I mentioned, the biggest immediate problem was getting
the generator working. I found there was one authorised dealer
for Onan generators and had them visit the boat. As it turned
out, they knew the boat from a previous time when it was moored
near Sydney.
After much prodding and poking they told me the electrical
problem was in fact a mechanical problem. They suggested a
new carburettor - cost $800+. At this stage I was having flashbacks
of hardware and software vendors arguing about whether the
problem related to the other person's hardware or the other
person's software.
I thought it cannot be that complex. It is a simple two cylinder
petrol engine. I removed the carby myself and took it to a
specialist carburettor company. They immediately pointed out
the float was leaking and charged me $80 to fix it and service
the carby. When I reinstalled it, the motor actually started
and ran for a while.
The generator is still not running perfectly so time to do
some more research. I found a web site (www.smokeskak.com)
devoted to Onan MCCK generators with an active forum. After
posting a request for help one night I woke up next morning
to find about 10 replies. The first suggestion was to replace
the points. After doing that, performance improved again and
it was fine for a few months.
Again it started to die but by this stage, I had found a
mechanic who had done a few bits and pieces on the boat and
knew how to fix things rather than replace components. Greg
spent some time with the motor and a service manual I had
bought over the Internet and improved the running. We are
still not there but getting closer all the time. The generator
runs reliably but is not working well under load. The priority
has dropped from 1 to 6.

Electrical
The wiring was always going to be a major issue. Anyone who
has had an old boat will tell you the same thing. If something
stops working, try rewiring it. Don't take out the old wires
however. Given almost 40 years of this approach there is probably
as much unused wiring as there is used wiring. A bunch of
wires disappear behind a bulkhead and pop out somewhere else.
Since there is virtually no colour coding, you have no idea
where wires start and stop.
I tried to group most of the wiring issues in a single group
of work. For weeks I chased wires and tested components. Lights
were replaced and terminals cleaned. Surplus wiring was ripped
out. Slowly the electrics started to come together.
In IT projects, testing can be done by either purchasing
some test tools, or doing it manually. If you are going to
do lots of testing you tend to buy testing tools as the time
and cost saving justifies the expense. With electrical testing,
there are some basic tools like a test lamp and a meter but
not much more. Necessity is the mother of invention.
Finding the other end of the wire is a tedious process. For
example, I wanted to find which wire provided power to the
instrument lights on the flybridge. I had a switch for instruments
on the dashboard inside the boat but no obvious wire heading
for the flybridge. There were potentially a dozen wires on
the flybridge that may have been providing instrument lights
with power at one stage.
I invented an intermittent voltage checker. Take one auto
flasher unit, a switch, a globe to make it work, put it in
a box and connect to the cigarette lighter plug. Add a wire
out with an alligator clip. Find a wire you want to trace
and clip the unit onto one end. You can now check the other
end for an intermittent voltage. Much easier than trying to
do continuity checks where the connection may be 10 or 15
metres away.
I had one funny experience when checking wiring to the flybridge.
There was a random wire that did not seem to be doing anything
on the flybridge. Connected "Turbit's Tester" to the wire
and turned it on. "Brrrr" pause "Brrrr" pause "Brrrr". Turns
out it was a spare starter wire. If you think of a starter
being turned in time with you blinkers you get the picture.

Maintain the Old
One problem worth noting from a project management perspective
was with the starter on one motor. As mentioned there were
dual controls. When I bought the boat there was no cover on
the flybridge so all the controls and instruments were exposed
to the weather even when the boat was not in use. I had not
worried about protecting the controls as I planned to eventually
have a cover made.
One day I was working on the boat and decided to run the
engines. I started them from the flybridge. The starter was
a key starter. Turn the key to start the motor then release
it.
A short time later I could smell something burning. After
I cut the motor I looked at the engine to find the starter
smouldering. Seems that after I started the motor, the key
had not released. The starter was still locked in although
the motor was running. Ten minutes later the starter melted.
The whole episode cost me around a thousand dollars by the
time I fixed it.

The view from the flybridge when I bought
the boat. The dash had lots of lights and switches that were
not connected to anything. They just filled holes. All were
removed and the holes filled and sanded before repainting.
The compass fluid leaked and drained away so it had to be
replaced. The seat frame was corroded and fell apart six months
later.
Had I paid attention to maintaining the existing controls
until the cover was made, I could have saved that money. Often
in a project we take a deep breath and rush to build something
new hoping that the old one will last until it is replaced.
It may be software, it may be hardware, it may be a bridge.
Sometimes we need to consider maintaining the old until the
new is ready.

How Long?
I mentioned a quality issue earlier in the article. After
purchasing my Cresta 34 I did some research on the make and
model but could find no reference to a 34 foot model. There
was a 32 foot model made around that period. I contacted the
manufacturer and spoke to a person who happened to be having
lunch with the original owner. The original owner was now
in his 90's. I provided some photos and evidently livened
up the lunch with some reminiscing about the model. He could
not remember building a 34 foot version but said there were
all sorts of modifications requested at the time and there
may have been one built.
Time to take out the tape measure. There is no real way to
measure a boat on a mooring so I had to wait until I was tied
up on a jetty to do a measurement. Guess what? My 34 must
have been in the water for so long it shrank. It is now 32
feet. Had I applied a little quality management I would have
verified all the details about the boat before purchasing.
While I could go back to the owner or broker, I would probably
hear that they bought it as a 34 footer and never checked.
There is nothing to gain. It does however show that in a project,
you need to QA all deliverables.

Refurbishment
Running your own business has good and bad points. My risk
of not being able to get time to do the refurbishment came
to fruition. It took me around 18 months to get the two weeks
I was looking for. In fact it ended up being fourteen days
over about six weeks. Fortunately all the other work meant
the boat was usable for about a year up to that time. The
final sub-phase was more about cosmetics - or so I thought.
By planning around splitting refurbishment from ongoing maintenance,
the boat was able to be used and I was not delayed from using
the boat.
Refurbishment went well until I detected the smell of petrol
in the bilge. Now I have tried many things in my life but
never had aspirations to be a suicide bomber. 400 litres of
fuel in a bilge is not my idea of fun. We had an issue.
The boat was on a marina having just been slipped and anti
fouled when the problem occurred. The shipwright I had been
using said to pull out the fibreglass tank and have a new
stainless steel one custom made. You could hear the cash register
ringing. Back to project management principles. When faced
with an issue look at all available options and select the
most appropriate. I had to find other options.
The problem was that at some stage someone had decided to
fit two new fuel outlets. Originally they had come out of
the top of the tank and had pipes that ran on the inside to
the bottom. The revised arrangement involved drilling a 15
mm hole in the side of the tank near the bottom and screwing
in a fitting. As the wall thickness was only about 5mm it
was never really a tight seal. It had been covered with silicon
sealant to stop it leaking but that had now failed.
Do some more research; gather more information; talk to anyone
who might be able to help. Eventually I found a fibreglass
repair shop. "If it is made of fibreglass, we can repair it." sounded
like good news. Next to remove the tank. If you have never
drained about 300 litres of fuel by using a 1 litre plastic
ice cream container, life still has a few experiences left
for you. I could just get a 1 litre container under the tap
and about three quarter fill it while lying across the tank
and holding the container at arms length in a gap between
the fuel tank and a water tank. Empty the ¾ litre into
a 20 litre container, then fill up all our family cars plus
those of a few friends. I was very popular. Anyway it is an
interesting way to spend a day.
The tank had to be cut out of the boat and lifted out by
a team of four. A week later the old holes had been filled
and the wall thickness built up to around 10 ml. Off to a
specialist firm who made up new fittings for the outlets and
we were back to the marina to fit the tank. The PM lesson
is that you don't need to jump to the first proposed solution
to an issue. Look at all the options. Sometimes a better one
will emerge with a bit of research.

Current State
We are almost there. The original list of 130 items eventually
blew out to 175 items but we had built in a 50% contingency
so in straight numbers, the increase was only 35%.

Arawa III as it is today. Rail around the
flybridge now stops people falling to their death. As an example
of the work involved, sanding the timber you can see around
the edge of the deck took 9 hours. There are four coats of
varnish that took around 2 hours each to apply. Total 17 hours.
Some problems turned out to be more complex so probably took
up the remaining 15% contingency although I suspect it was
closer to 20% to 25%. Not bad if we were only 10% over in
terms of effort.
There are currently 11 items left to be completed and of
those the 4 largest are 90% complete. The current estimate
is 3 to 5 days to complete the list. Given the time spent
recently away from my business, and the catching up to do,
that might well mean Christmas before the list is complete.
Of course there are a number of new projects identified however
they are more in the area of improvements. The original scope
which was to fix what was there rather than add improvements.
It is always tempting to let the scope creep, but fortunately
some project management experience kicked in here and I overcame
the temptation.

Conclusion
We
don't necessarily think of work at home or on a hobby as a
project, but it can help to do it that way. I was certainly
not as rigorous in restoring the boat as I would be in a business
related project. I did - almost through habit - use a number
of PM skills and they certainly made life easier. Some of
the problems I had could be traced back to not using those
PM disciplines. Quality management was one area I did fail
in a number of cases. Tighter quality management would have
avoided a few issues.
Project management is a whole of life skill. I have long
advocated that project management principles should be taught
to young kids at school. It would make us
all better at "getting things done". I hope that by telling the
story of buying and fixing up a boat, you will see that there is
a role for project management in all our lives.
The final question of course is power boating more fun than
sailing. I have to confess I am still a sail boat person.
One day I will probably go back to it or just get myself a
small boat I can tow on a trailer and sail on my own. Until
then, I can still enjoy Sydney Harbour with friends. I suddenly
seem to have found a lot more people who want to be my friend.

To date,
18 people have rated this article. The average rating is
4.22 - Add your rating. Just select a rating and click the button.
No other information required.
Only one rating per person is allowed.
|
Arawa III
|

Return to the top

|